Bullhead City Launches Citywide Maintenance and Capital Improvement Projects Week of October Nineteen
BULLHEAD CITY, Arizona, October 16, 2026 – Bullhead City staff, City contractors, and utility companies within City...
Bullhead City, Arizona, September 4, 2026
Bullhead City staff, City contractors, and utility companies will be conducting several maintenance and capital improvement projects during the week of September 7. The projects include:
• The ADA ramp at the Rotary Park fishing pier will be closed beginning September 8 while crews complete accessibility upgrades. This work is expected to last one month.
• City street maintenance crews will be working on the paved walking trail at Ken Fovargue Park. The work, which involves tree trimming, debris removal, and crack sealing, will be performed while the trail remains open. Trail-goers are encouraged to exercise caution around working crews.
• Construction continues on laying a new waterline along North Oatman Rd as part of Phase III of the South Supply Line project. This project will connect the new well on Riverview Dr to a future water tower on Black Mountain Rd.
• In partnership with Northern Pipeline Construction Co. (NPL), Southwest Gas will be installing a new gas main along Bullhead Parkway between Laughlin Ranch Boulevard and Landon Drive throughout September. Work will be performed daily from 5 a.m. to 6 p.m. and will require intermittent lane restrictions at the intersection of Bullhead Parkway and Laughlin Ranch Boulevard, as well as southbound right-lane closures along Bullhead Parkway. No full road closures are anticipated, and access through the area will be maintained.
• T.R. Orr, Inc. is continuing the construction of new restrooms at Community Park, located just south of the Bullhead Belle.
• Contractors on behalf of Bullhead City Utilities will complete various asphalt and concrete repairs throughout the city in areas where recent water line repairs were made.
• Kay Constructors LLC, under contract with Bullhead City Utilities, is building a new aeration basin at the Section 10 wastewater treatment plant as part of an overall expansion effort to boost reclaimed water volume.
• Bullhead City Utilities will also proceed with rehabilitating a clarifier at the Section 10 wastewater treatment plant (901 Richardo Ave). This project includes the draining, cleaning, and measuring of the existing clarifier before installing new mechanical equipment and protective material to extend its service life.
• Kay Constructors is additionally constructing a new clarifier at the Section 10 wastewater treatment plant.
Residents can receive road closure notices and project updates by downloading the Bullhead City Direct app, available for Android and iOS devices. The app serves as the public’s direct line to City Hall, allowing residents to receive timely updates and report issues directly to City Staff.
The City advises residents to only flush human waste, toilet paper, and grey water down the drain. All other waste should be disposed of by alternative means to protect the City’s infrastructure. While traveling through work zones, motorists should obey posted signage and traffic control devices.
For additional information on ongoing projects throughout the City, please visit bullheadcity.com/BullheadCityDirect.
BULLHEAD CITY, Arizona, October 16, 2026 – Bullhead City staff, City contractors, and utility companies within City...
BULLHEAD CITY, AZ, October 16, 2026 — The highly popular splash pad at Community Park is temporarily closed for...
For Immediate Release BULLHEAD CITY, Arizona — Meals on Wheels of Bullhead City, AZ is giving the community two easy...
0 Comments